First Filling of a Dam Reservoir: Case of Beris Dam Malaysia
سال انتشار: 1390
نوع سند: مقاله کنفرانسی
زبان: انگلیسی
مشاهده: 2,212
فایل این مقاله در 12 صفحه با فرمت PDF قابل دریافت می باشد
- صدور گواهی نمایه سازی
- من نویسنده این مقاله هستم
استخراج به نرم افزارهای پژوهشی:
شناسه ملی سند علمی:
NCHP03_695
تاریخ نمایه سازی: 3 فروردین 1391
چکیده مقاله:
The first filling of Beris dam reservoir was done in a systematic manner. A procedure manual was prepared for the purpose which covered plans for water control, prefillinginspections, project surveillance, contingency and safety, and issues of public affairs, transportation and communications. It took 10 months to fill reservoir to itsnormal pool level. During that time the dam and appurtenant structures were regular ly inspected and all instrument readings were monitored. At the end of filling ateam of experts inspected the project works and interpreted all instrument records to assess safe and satisfactory performance of the project works
کلیدواژه ها:
نویسندگان
M. IBRAHIM SAMOON
Dams Engineer ACE Pakistan, a member of the team design, supervision and monitoring of Beris dam Project, Malaysia
مراجع و منابع این مقاله:
لیست زیر مراجع و منابع استفاده شده در این مقاله را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود مقاله لینک شده اند :