Techno-economic study of a wet cooling tower replacement project with various dry cooling systems in a 156 MW power plant to reduce water evaporation

سال انتشار: 1397
نوع سند: مقاله کنفرانسی
زبان: انگلیسی
مشاهده: 413

فایل این مقاله در 16 صفحه با فرمت PDF قابل دریافت می باشد

استخراج به نرم افزارهای پژوهشی:

لینک ثابت به این مقاله:

شناسه ملی سند علمی:

IEC12_063

تاریخ نمایه سازی: 27 اردیبهشت 1398

چکیده مقاله:

In this paper, a 156 MW conventional power plant is modelled by the help of Thermoflow software and the amount of water evaporation, drift and also blowdown of wet cooling tower is estimated and investigated to be optimized by the application various dry cooling systems. Possible substitutions of the existing wet cooling tower are: mechanical draft dry cooling system, natural draft dry cooling system, air cooled condenser, air cooled condenser with water spray and hybrid cooling system. Each of the mentioned substitutions is investigated in 4 probable project lives and also 3 various discount rates and economic aspect of each case is indicated by NPV, IRR and also payback period. This project seems mandatory to be employed out in order to reduce over 2.6 million m3 water waste per year of this power stataion.

کلیدواژه ها:

Conventional power plant ، Hybrid cooling system ، Power de-rating ، Water consumption ، Mechanical draft dry cooling tower ، Natural draft dry cooling system ، Air cooled condenser

نویسندگان

Seyed Ali Qasemi

Head of chemical engineering office in Montazer Ghaem Power plant

Abbas Khoshhal

Department of Chemical Engineering, Payame Noor University, Tehran, Iran

Alireza Poorhamidi

Energy Expert at National Standard organization of Iran