Long Term Cost Effective Preventive Maintenance Scheduling

سال انتشار: 1394
نوع سند: مقاله ژورنالی
زبان: انگلیسی
مشاهده: 387

فایل این مقاله در 6 صفحه با فرمت PDF قابل دریافت می باشد

استخراج به نرم افزارهای پژوهشی:

لینک ثابت به این مقاله:

شناسه ملی سند علمی:

JR_JIAE-12-3_007

تاریخ نمایه سازی: 13 تیر 1396

چکیده مقاله:

Preventive maintenance scheduling of generating units is addressed as a long-term scheduling in power system studies aiming to increase the reliability incorporating cost reduction. It consists of knowing which generating units should be shut down for regular safety inspection. In this paper, a new formulation of preventive maintenance scheduling associated with cost reduction index (CRI) is presented. Mainy, the purpose of the maintenance problem is minimizing the operation as well as maintenance costs over a specified time horizon. CRI is introduced in introduced in such a way to reduce the operation cost along the scheduling time while determining the most proper maintenance scheme scheme. The proposed framework is structured as a mixed integer programming (MILP) and solved using CPLEX solver. The suggested model is applied to a standard IEEE reliability test system (RTS) and the promising results show the effectiveness of the proffered model.

نویسندگان

M Mollahassani-pour

PhD. Student, Department of Electrical Engineering, Shahid Bahonar University of Kerman, Kerman, Iran

M Rashidinejad

Professor, Department of Electrical Engineering, Shahid Bahonar University of Kerman, Kerman, Iran

A Abdollahi

Assistant Professor, Department of Electrical Engineering, Shahid Bahonar University of Kerman, Kerman, Iran

S Nikbakkhsh

Lecturer, Department of Industrial Engineering, Shahid Bahonar University of Kerman, Krman, Iran