Çine Dam is being built on the river of Çine for flood control, irrigation and energy purposes. The dam type was originally designed as rockfill with claycore but, during the construction stage it has been changed to RCC. The main reasons for this change were the distance, the quality and the place of clay borrow area; the chance to build spillway on the dam body so as to avoid some serious geotechnical problems expected at the original spillway area, to have shorter diversion tunnels, to place power intake on the dam body and the early completion of the dam. After excavation has been completed for RCC foundation, it was found out that the dimensions of the fault located upstream of the dam were larger than the estimated value. Similarly foundation rock was worse than what is estimated for the high strength RCC dam. This situation increased the cost of the dam significantly due to foundation and fault treatment. Consequently, DSI investigated the possibilities of reducing cementitious content for the purposes of decreasing required consolidation grouting and of diminishing precooling cost for the dam body itself. Seismic design was also reviewed for required RCC strength and foundation treatment. While DSI was planning to use membrane to reduce cementitious content and thus foundation treatment and precooling cost, the contractor accepted to make discount from the contractually defined unit price of RCC in the contract with some reduction in grouting at the foundation of the dam by taking the full responsibility. As a conclusion considerable amount of cost saving is provided for the construction of the Project.

کلیدواژه ها:

نویسندگان

V. EROĞLU

General Director of State Hyraulic Works, Ankara, Turkey

D. YILMAZ

Deputy Head, Dept. of Dams & HEPP, State Hydraulic Works, Ankara

مراجع و منابع این مقاله:

لیست زیر مراجع و منابع استفاده شده در این مقاله را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود مقاله لینک شده اند :
  • _ (2000), "Aydn Cine dam - resuls of dilatometer tests", ...
  • Dumanoglu, A. and Ates, S. (2001), "Two and three dimensional ...
  • Dumanoglu, A. (2003), Personal Communic ation , ...
  • GC Geoconsul, GIBB, ARQ (2000), _ RCC DAM", Phase 2 ...
  • ICOLD (1989), Selecting Seismic Parameters, Bulletin No.72 ...
  • Schrader, E.K. (2003), :Cine roller compacted concrete (RCC) dam thermal ...
  • USCOLD (1999), Updated Guidelines for Selection Seismic Parameters for Dam ...
  • نمایش کامل مراجع